Generator, Rotor and Stator Cleaning

Dry-Ice-Case-Study-Generator-Cleaning-500x320

Industry: Power Generation

Location: Australia-Power Station

Circumstances: Programmed maintenance shutdown of Alstom Type T190-240 rated at 48MVA generator Cleaning options:

  • Chemical Cleaning: 7 to 10 days with 6 people utilizing electrical cleaning chemicals
  • Dry Ice Cleaning: 3 days to clean utilizing 2 personnel & dry ice machinery
  • Chemical Cleaning: 7 to 10 days with 6 people utilizing electrical cleaning chemicals
  • Dry Ice Cleaning: 3 days to clean utilizing 2 personnel & dry ice machinery
  • More than 4 days saved over traditional manual cleaning meaning the equipment was back making money much quicker
  • Cleaning was much more through, as dry ice was able to access many of the small spaces impossible to access by hand.